Procurement control
Procurement Items
Review releases by approval dependency, lead time, PO status, and required on-site date so long-lead glazing material does not surprise the project team.
2 records
Procurement Queue
Curtain wall framing and anchors
Waiting For ApprovalRiverfront Medical Office Building / Midwest Architectural Metals
Found at: Spec 08 44 13 Glazed Aluminum Curtain Walls; submittal SUB-001 (Curtain wall and storefront elevations, anchors, movement joints, glass types, and hardware coordination.).
Requirement summary: approval needed Apr 22, 2026, release Apr 25, 2026, lead time 84 days, required on site Jul 20, 2026.
Low-e insulated glass units
Ready To ReleaseRiverfront Medical Office Building / ClearLine Glass
Found at: Spec 08 80 00 Glazing; submittal SUB-003 (Clear anodized finish, low-e IGU sample, laminated glass sample, and fire-rated glazing label sample.).
Requirement summary: approval needed Apr 10, 2026, release Apr 15, 2026, lead time 56 days, required on site Jul 20, 2026.