Contract intelligence
Open Contract Risk
Click any risk to view the source clause, why it matters, and the editable strikeout/replacement language. Admins, executives, and PMs can update records when they have project access.
3 records
Risk Queue
Backcharge notice
MediumRiverfront Medical Office Building / GPC-24017
Subcontract / page 12: Contractor may supplement or backcharge Subcontractor without prior notice where Contractor deems necessary.
Without notice and cure rights, disputed field issues can become unilateral deductions.
Updated Jun 11, 2026
Pay-if-paid payment condition
HighLegal ReviewRiverfront Medical Office Building / GPC-24017
Subcontract / page 6: Payment to Subcontractor is expressly conditioned upon Contractor's receipt of payment from Owner.
This can shift owner non-payment risk to the glazing subcontractor even after acceptable work is performed.
Updated Jun 11, 2026
Liquidated damages flow-down
CriticalLegal ReviewRiverfront Medical Office Building / GPC-24017
Subcontract / page 9: Subcontractor shall be liable for all damages, penalties, acceleration costs, and liquidated damages arising from delay.
The clause is uncapped and may expose the glazier to project-wide damages beyond its proportionate responsibility.
Updated Jun 11, 2026