Riverfront Medical Office Building / GPC-24017 / Northstar Builders
Application: #1
Period To: May 31, 2026
Status: DRAFT
Original Contract: $1,842,500
Net Change Orders: $66,500
Contract Sum To Date: $1,909,000
Total Completed + Stored: $0
Retainage: $0
Current Payment Due: $0
| Line | Description | Spec | Scheduled Value | Previous | Current | Stored | Balance |
|---|---|---|---|---|---|---|---|
| 1 | Glazed Aluminum Curtain Walls | 08 44 13 | $760,000 | $0 | $0 | $0 | $760,000 |
| 2 | Aluminum Storefronts and Entrances | 08 41 13 | $410,000 | $0 | $0 | $0 | $410,000 |
| 3 | Glass and Glazing | 08 80 00 | $455,000 | $0 | $0 | $0 | $455,000 |
| 4 | Perimeter Sealants | 07 92 00 | $86,000 | $0 | $0 | $0 | $86,000 |
| 5 | Shop Drawings, Engineering, Submittals | 01 33 00 | $124,000 | $0 | $0 | $0 | $124,000 |
| 6 | Closeout and Warranty | 01 78 00 | $74,000 | $0 | $0 | $0 | $74,000 |