Project Health

78/100

2 high or critical contract risks

Revised Contract

$1,909,000

Original $1,842,500

Submittals Approved

1/3

Approval drives procurement release

Missing Admin Docs

2

Insurance, payroll, tax, and execution documents

Project health

Command Dashboard

Schedule Warnings

2

Approval and lead-time conflicts

Procurement Warnings

1

Waiting on submittal approval

Uploaded Documents

1

Indexed for analysis

Submittal approval needed for material release

Blocked

Curtain wall release is blocked by R&R comments.

Release curtain wall framing

Not Started

Any approval slip after Apr 22 pushes installation.

Project AI Assistant

Answers from project data and uploaded document analysis.

Project setup

Sales Order

Active

Customer Contact

Dana Miller / [email protected]

Architect

Klein Hart Design Group

Owner

Riverfront Health Partners

Bid / Award

Jan 18, 2026 / Feb 9, 2026

Required Completion

Nov 20, 2026

Retainage

10%

Tax Status

Tax exempt materials certificate required before releases

Union

Union field labor

Billing

Monthly AIA G702/G703 percent complete billing

Scope Summary

Exterior aluminum curtain wall, storefront, entrances, insulated glass, fire-rated interior glazing, brake metal, perimeter sealants, delegated engineering, shop drawings, submittals, and closeout warranties.

Document center

Document Upload + AI Analysis

Drag and drop PDFs, text files, or project documents

Multiple files are supported. Each file is stored, indexed, and analyzed.

Auto-populate workspace from uploaded documents

Reads indexed subcontract/spec/plan text and creates scope sections, risks, submittals, procurement, schedule items, admin docs, and AIA SOV lines.

Riverfront Subcontract.pdf

Subcontract / 3772 KB

Subcontract covers exterior curtain wall, storefront, glazing, entrances, delegated design, and closeout for the Riverfront Medical Office Building.

Open a section for scope intelligence

Glazing Scope + Specification Sections

08 44 13

Glazed Aluminum Curtain Walls

Pressure-equalized curtain wall framing, low-e IGUs, spandrel panels, anchors, perimeter fire safing coordination, shop drawings, structural calculations, and field testing.

Sheets: A201, A301, A502, A701

Details: A502/4 head, A502/7 sill, A701/2 vertical mullion at slab edge

Submittals: Product data, shop drawings, structural calculations, finish samples, glass samples, thermal performance data, warranty.

Testing: AAMA 501.2 hose testing, ASTM E283/E331/E330 performance reports.

Delegated design: Licensed engineer must design anchors, mullions, movement joints, and dead/live load reactions.

Warranty: 10-year curtain wall system warranty and 10-year IGU warranty.

Closeout: Final warranties, maintenance instructions, cleaning recommendations, as-built elevations.

Notes/Risks: Lead time is sensitive to approved finishes and engineering comments. Coordinate slab edge embeds before field measurements.

08 41 13

Aluminum-Framed Entrances and Storefronts

Thermally broken storefront, medium stile entrances, closers, panic hardware coordination, thresholds, weatherstripping, and perimeter sealants.

Sheets: A101, A401, A601

Details: A401/3 entrance jamb, A601 door schedule notes 14-19

Submittals: Product data, shop drawings, hardware schedule coordination, finish samples, glass samples.

Testing: Air, water, structural test data for storefront framing.

Delegated design: Engineering required for large vestibule openings over 10 feet tall.

Warranty: 2-year entrance hardware and 5-year storefront finish warranty.

Closeout: Hardware maintenance sheets, keying coordination record, warranty letters.

Notes/Risks: Door hardware is split-scope with Division 08 hardware supplier; coordination needed before shop drawing approval.

08 80 00

Glazing

Insulated, tempered, laminated, fire-rated, and interior glass types with setting blocks, spacers, sealants, and labels.

Sheets: A601, A602, A801

Details: A602 glass type schedule, A801 interior borrowed lite details

Submittals: Glass product data, safety glazing certificates, fire-rated listing data, samples, warranty.

Testing: Safety glazing compliance and IGU thermal performance.

Delegated design: Confirm glass thickness by wind load and opening size.

Warranty: 10-year IGU seal warranty and manufacturer fire-rated glazing warranty.

Closeout: Glass care instructions, warranty certificates, final glass type list.

Notes/Risks: Fire-rated glass at stair enclosures cannot be substituted without AHJ approval.

Project-management risk assistance

Subcontract Review

Print Review

This app is not a law firm and does not provide legal advice. It provides project-management review assistance only.

Editable register generated from subcontract, plans, and specs

Submittal Register

Add manual submittal
IDSectionDescriptionDueResponsibleStatusRevisionFiles
SUB-00108 44 13Curtain wall and storefront elevations, anchors, movement joints, glass types, and hardware coordination.Mar 20, 2026Drafting ManagerRevise And ResubmitRev 1
SUB-00208 44 13Delegated design calculations for curtain wall, storefront, anchors, and glass thickness.Mar 27, 2026Engineering ConsultantSubmittedRev 0
SUB-00308 80 00Clear anodized finish, low-e IGU sample, laminated glass sample, and fire-rated glazing label sample.Apr 3, 2026Project CoordinatorApproved As NotedRev 0

Dependencies from submittal approval to installation

Project Schedule

Add manual schedule item
ItemCategoryStartFinishDependencyStatusWarning
Subcontract reviewedContractFeb 17, 2026Feb 21, 2026Subcontract receivedComplete
Initial submittals dueSubmittalsMar 14, 2026Mar 20, 2026Sales order completeComplete
Submittal approval needed for material releaseSubmittalsApr 8, 2026Apr 22, 2026Architect reviewBlockedCurtain wall release is blocked by R&R comments.
Release curtain wall framingProcurementApr 23, 2026Apr 25, 2026Approved shop drawings and calculationsNot StartedAny approval slip after Apr 22 pushes installation.
Curtain wall installationFieldJul 27, 2026Sep 18, 2026Material delivered and openings readyNot Started
Punch list and closeoutCloseoutOct 26, 2026Nov 13, 2026Field installation completeNot Started

Lead times tied to required on-site dates

Procurement Log

Add manual procurement item
ItemSectionVendorApproval NeededReleaseLead TimeOn SitePOStatus
Curtain wall framing and anchors08 44 13Midwest Architectural MetalsApr 22, 2026Apr 25, 202684 daysJul 20, 20265000Waiting For Approval
Low-e insulated glass units08 80 00ClearLine GlassApr 10, 2026Apr 15, 202656 daysJul 20, 20265001Ready To Release

PO numbering starts at 5000

Purchase Orders

Print
Create Purchase Order

PO 5000

Midwest Architectural Metals

Riley Foster, [email protected]

Draft

Delivery: Jul 20, 2026 to 1200 Riverfront Parkway, St. Louis, MO

Total: $630,500

Printable PO

PO 5001

ClearLine Glass

Taylor Kim, [email protected]

Draft

Delivery: Jul 20, 2026 to 1200 Riverfront Parkway, St. Louis, MO

Total: $462,000

Printable PO

RFC to customer approval to internal CO

Change Orders

Add manual RFC / change order
RFCTitleCauseSubmittedStatusSchedule ImpactChange Order
RFC3Add fire-rated glazing at stair vestibulesASI / design revisionApr 8, 2026ApprovedAdds two weeks to specialty glass lead time unless released by May 1.RFC3 / CO2 / Customer CO-007

AIA-style progress billing plus standard invoice fallback

Billing

Print AIA BillingPrint Invoice

AIA-style progress billing

Use this when the customer, owner, architect, or GC requires a progress billing package tied to a schedule of values.

Standard invoice fallback

Use the invoice when a customer does not require AIA billing or needs a simpler direct bill from the same project values.

Application

#1

Period to May 31, 2026

Contract Sum

$1,909,000

COs $66,500

Completed + Stored

$0

Retainage $0

Current Payment Due

$0

Balance $1,909,000

Draft
LineDescriptionSpecScheduled ValuePreviousCurrentStoredRetainage %
1
2
3
4
5
6

Financial health connected to contract, changes, procurement, billing, and schedule

WIP Report

Print

Current GP

$389,200

Estimated GP $421,000

Percent Complete

18%

Billed $298,000

Underbilling

$45,620

Retainage $29,800

Risk notes: Profit at risk if curtain wall approval slips or fire-rated glass premium is not fully captured.

Front-end compliance checklist

Insurance + Admin Documents

CategoryStatusDueExpirationResponsibleNotes
Certificate of insuranceApprovedFeb 28, 2026Feb 28, 2027Project CoordinatorAccepted by GC.
Certified payroll documentsRequestedJul 20, 2026Not setPayrollRequired before field labor mobilization.
OCIP / CCIP formsReceivedMar 5, 2026Not setSafety ManagerAwaiting GC enrollment confirmation.
Subcontract execution documentsReceivedFeb 26, 2026Not setProject ManagerPending final negotiated rider.
Tax exemption certificateMissingApr 15, 2026Not setAccountingNeeded before glass and aluminum POs are issued.

Access and project controls

Settings

Defaults are set for glazing operations: executives see financial health, PMs run project controls, estimators focus on scope and change pricing, accounting owns billing/WIP, and field users see schedule/admin/submittal information. Admins can change any position manually.

Accounting
Admin
Estimator

Executive Viewer

[email protected]

Executive
Field

Project Manager

[email protected]

Project Manager

Customer Viewer

[email protected]

Viewer
RoleDashboardSalesorderDocumentsContractreviewSubmittalsScheduleProcurementPurchaseordersChangeordersWipBillingAdmindocsSettingsCaneditCanapproveSave

Admin

Full system control.

Executive

Executive visibility into risk, WIP, billing, and schedule health.

Project Manager

Daily owner of project controls and document-driven workflows.

Estimator

Scope, changes, procurement assumptions, and handoff support.

Accounting

AIA billing, WIP, POs, lien waivers, tax, and admin documents.

Field

Field visibility into schedule, submittal status, admin constraints, and documents.