Glazing Project Command Center
Project Schedule
Riverfront Medical Office Building / GPC-24017 / Northstar Builders
| Item | Category | Start | End | Dependency | Status | Warning |
|---|---|---|---|---|---|---|
| Subcontract reviewed | Contract | Feb 17, 2026 | Feb 21, 2026 | Subcontract received | Complete | |
| Initial submittals due | Submittals | Mar 14, 2026 | Mar 20, 2026 | Sales order complete | Complete | |
| Submittal approval needed for material release | Submittals | Apr 8, 2026 | Apr 22, 2026 | Architect review | Blocked | Curtain wall release is blocked by R&R comments. |
| Release curtain wall framing | Procurement | Apr 23, 2026 | Apr 25, 2026 | Approved shop drawings and calculations | Not Started | Any approval slip after Apr 22 pushes installation. |
| Curtain wall installation | Field | Jul 27, 2026 | Sep 18, 2026 | Material delivered and openings ready | Not Started | |
| Punch list and closeout | Closeout | Oct 26, 2026 | Nov 13, 2026 | Field installation complete | Not Started |