Glazing Project Command Center
WIP Report
Riverfront Medical Office Building / GPC-24017 / Northstar Builders
Original Contract
$1,842,500
Approved Change Orders
$66,500
Revised Contract
$1,909,000
Estimated Cost
$1,488,000
Committed Cost
$1,092,500
Actual Cost
$238,400
Current Gross Profit
$389,200
Billed To Date
$298,000
Retainage
$29,800
Cash Position
-$15,200
Risk notes: Profit at risk if curtain wall approval slips or fire-rated glass premium is not fully captured.